A two-month kitchen becomes five when the wait is left off the plan.
The weeks someone is swinging a hammer are not the whole job. Cabinets, the countertop template, fabrication, and the inspection each take their own time. None of the numbers below is a promise for your order.
What a survey actually reported
In the NKBA Kitchen & Bath Market Index for the third quarter of 2024, firms reported average lead times of about 7.9 weeks for cabinets and about 3.4 weeks for countertops in one segment of the survey. In the manufacturing segment of the same report, countertops were reported at about 7.4 weeks. Those are survey averages from that quarter. They move. They are not your shop's date, and they are not a Florida price.
Source: NKBA and John Burns, Kitchen & Bath Market Index, Q3 2024 (PDF).
A typical sequence, labeled as an example
One ordinary order of work, not a guarantee: cabinets are ordered and then set; the countertop shop templates off the installed cabinets; fabrication follows the template; then the stone is installed. A shop may tell you fabrication takes about two to three weeks after the template. Treat that as an example until your shop writes the date. If the quote only says "kitchen, eight weeks," ask which of these steps sit inside those eight weeks.
Permitted work also waits on the building department. The 2021 International Residential Code, R105.1, requires a permit before regulated construction and before regulated electrical, mechanical, and plumbing work. Your city decides the inspections. Do not cover work the inspector still has to see. That hold is another reason a short plan slips.
Source: 2021 IRC R105.1, International Code Council.
Put the dates you were actually given on the timeline in the Remodel Budget & Schedule Kit. The sheet does not invent a lead time for you.
Questions
Is two to three weeks of fabrication a promise?
No. On this page it is an example of the step after the template. A 2024 industry survey reported longer averages. Your shop's date is the one that counts.
Why does a two-month kitchen become five?
The two months often count only the weeks someone is in the house. Cabinet lead time can already be about two months, and the template, fabrication, and an inspection hold come after that. Those weeks stack.
Where do I put my real dates?
On the timeline tab of the Remodel Budget & Schedule Kit, using the lead times your suppliers actually quote. This page does not schedule your job.